NW Beaver Drive Overlay

Project Description
NW Beaver Drive – Merle Hay Rd. to North Corporate Limits
HMA (Asphalt) mill and overlay project along NW Beaver Drive from Merle Hay Road to the North Corporate Limits (approximately 3.25 miles). Project will include median/splitter island in locations along with recreational trail.

Project Update (as of 8/29/18)
Paving did not occur on Tuesday, Aug. 28 as the weather conditions were sporadic for the contractor to safely work. The contractor has NOT modified the schedule and plans for full closures on Thursday, Aug. 30 and Friday, Aug. 31. Please see below for the specifics. Trail paving work will also occur during this time rather than Wednesday.

  • Thursday, Aug. 30 - 9 a.m. to 3 p.m. 
  • Friday, Aug. 31 - 9 a.m. to 3 p.m. 
  • Thursday’s extents will be from south of Theresa Drive to south of the Hyperion Field Club Entrance
  • Friday’s extents will be from south of the Hyperion Field Club entrance to Merle Hay Road
  • The contractor will work from north to south each day and open the road as they complete sections
Please continue to use caution and lower speeds when driving through the construction site. If the schedule changes, notification will be made as soon as possible.

Please keep in mind that all of this is weather dependent and could change very quickly. If the work needs to be postponed, notifications will be sent out.

Please use caution through the work zone and use low speeds.

Click here (PDF) to view the presentation from the meeting on March 21, 2018. 
Click here (PDF) to view the letter sent March 12, 2018 to residents within the project area.  

Project Information
On August 24, a public open house was held to discuss the improvements to NW Beaver Drive. Click here (PDF) to view the presentation given by Foth at the public meeting. Click here (PDF) to view the maps of construction stages.  

Estimated Cost
Estimated Cost as of 8/7/2017 is $4,325,764.00

Contractor
Grimes Asphalt & Paving

Estimated Project Timeline
Construction anticipated to begin late August and finish by mid to late November.

Engineer Design
Nicole Sungren, MSA Professional Services


Construction Administration
Amy Quartell, Foth Infrastructure
515.251.2531
Email Amy

City Staff Project Contact
Matt Greiner, Public Works Director
515.278.0822
Email Matt Greiner