Beaver Creek Bridge and Bank Stabilization

The Beaver Creek Bridge and bank stabilization project is scheduled for construction this summer and will continue into fall. The project will include stabilizing the footings of the bridge and the shoreline around the bridge. It will consist of relocating two sections of the trail to ensure they do not fall into Beaver Creek. These sections are immediately east of the bridge and the trail area that winds along Beaver Creek adjacent to the area where the bridge is located.

The trails will be relocated to ensure they are secure and one trail will wind past the oxbow in the Beaver Creek Natural Resource Area.

On Tuesday, June 15, a public informational meeting will be held at 5:30 p.m. at Crown Point Community Center. This meeting will provide residents an opportunity to ask questions and understand the project.

Project Area Map
Click here (PDF) to view the map.

Public Information Meeting
Tuesday, June 15
5:30-7 p.m.
Crown Point Community Center, 6300 Pioneer Pkwy., Johnston, IA 50131

Estimated Cost
$357,748.25

Schedule
Summer-Fall 2021

Contractor
Howrey Construction

Engineer
Email Blair Spotts
Foth Infrastructure and Environment

City Staff Project Contact
John Schmitz, Parks & Recreation Director
(515) 727-8091
Email John Schmitz

 

Images before the stabilization begins

5. Beaver Creek Stabilization_Bridge_June 2021
4. Beaver Creek Stabilization_June 2021
3. Beaver Creek Stabilization_June 2021
1. Beaver Creek Stabilization_June 2021
6. Beaver Creek Stabilization_Trail_June 2021