Windsor & NW 100th St Interim Improvements

Project update: (10/17/2020)
The Roadway improvements are now complete. The disturbed area has been stabilized and restoration seeding will be complete in the spring.
Project Description

This project involves widening the pavement at the intersection of Windsor Parkway and NW 100th Street to accommodate the addition of designated turning lanes.  This will improve traffic flow through this intersection making this area safer for traffic and pedestrians.

Attached is a map of the area of construction.

Project Completion Date:
October 2, 2020

Estimated Cost:
$80,843.86

Contractor:
InRoads, LLC

Engineer:
Foth Infrastructure & Environment, LLC
Molly Long515-251-2591
Email Molly Long

City Staff Project Contact:
Matt Greiner, Public Works Director
515.278.0822
Email Matt Greiner