NW 54th Avenue-NW 86th St to NW 100th St

Project Description
The improvements include reconstruction of the existing two-lane rural roadway typical section to a three-lane and four-lane urban typical roadway section.  The existing four-lane sections will continue east of NW 100th Street and transition down to a three-lane section just east of the intersection of NW 93rd Street.  These improvements will be including the intersections of NW 96th St, NW 93rd Street, NW 91st Street, NW 91st Court, NW 90th Court, NW 89th Court, and NW 88th Street with NW 54th Avenue.

The project will consist of both 7" and 9" PCC, 10ft multi-use pathway, storm sewer, sub-drains, sanitary sewer, lighting, underground power, private utility relocation, pavement markings, signage, and surface restoration.

Project Update (7/19/2021)

The week of July 19th, the grading contractor will finish soil grading and install the granular subbase on the west end of Phase II from east of NW 89th Court to east of NW 93rd Street.  The drainage contractor will finish the sub-drain installation on the south side of NW 54th Avenue.  The fence in front of the West Prairie Townhomes is being scheduled to be installed by the end of July.  

For the week of July 26th, the paving contractor will begin trimming the granular subbase for NW 54th Avenue paving.  Paving portions of the trail, sidewalks, and remaining driveways will also be done this week. 
 
Public Communication
View the March 25, 2021 presentation below for more information about the project, or click here (PDF) to view it too. 

Project Information

Estimated Cost
$4,557,673.60

Contractor
Alliance Construction Group, LLC

Estimated Project Timeline
  • Construction Phase 1 (NW 100th Street to NW 93rd St) 2020
  • Construction Phase 2 (NW 93rd St to NW 86th Street) 2021

Engineer Design
Mike Lyons, Project Engineer
515.608.6003
mlyons@sehinc.com

City Staff Project Contact
Matt Greiner, Public Works Director
515.278.0822
Email Matt Greiner